Below is the construction sequence used following the Vans construction manual.
EMPENNAGE
Horizontal Stabilizer
January 9, 2003
January 14, 2003 (4hrs)
January 20, 2003 (2hrs)
January 21, 2003 (3 hrs)
January 29, 2003 (3hrs)
February 03, 2003 (4hrs)
February 15, 2003 (8hrs)
February 16, 2003 (10hrs)
February 17, 2003 (10hrs)
February 18, 2003
(8hrs)
Vertical Stabilizer
March 3, 2003 (8hrs)
March 7, 2003 (7hrs)
Rudder
March
12, 2003 (7hrs)
March
17, 2003 (9hrs)
April
21, 2003 (9hrs)
April 28, 2003 (3hrs)
May 05, 2003 (7hrs)
Elevators
May 26, 2003 (5hrs)
June 10, 2003 (6hrs)
July 03, 2003 (9hrs)
July 07, 2003 (6hrs)
July 30, 2003 (6hrs)
August 08, 2003 (2hrs)
Wings
August 17, 2003 (8hrs)
August 28, 2003 (7hrs)
October 08, 2003 (4hrs)
December 19, 2003 (4hrs)
January 05, 2004 (6hrs)
January 08, 2004 (4hrs)
January 15, 2004 (9hrs)
January 19, 2004 (6hrs)
February 2, 2004 (12hrs)
February 12, 2004 (7hrs)
February 25, 2004 (12hrs)
May 22, 2004 (15hrs)
July 12, 2004 (12hrs)
July 27, 2004 (4hrs)
August 07, 2004 (13hrs)
August 16, 2004 (12hrs)